AB 6 (Sub-No. 413X)
Docket Yard · docketyard.org/d/AB-6/sub/413X · entries shown: all, newest first
BNSF RAILWAY COMPANY--ABANDONMENT EXEMPTION--IN WASHINGTON COUNTY, MN
Caption from the Board’s record.
7 filings, 7 decisions and 15 environmental comments observed here; last checked 11 Oct 2026, 00:36 UTC; last new entry 31 Aug 2026, 20:17 UTC.
Entries
-
(printed as 9/22/2006)Notice217611Consummation NoticeBnsf Railway Company
-
served (printed as 6/27/2006)DecisionDECISION GRANTED BNSF RAILWAY COMPANY'S REQUEST FOR AN EXTENSION OF TIME TO EXERCISE ABANDONMENT AUTHORITY ON OR BEFORE DECEMBER 31, 2006.
-
(printed as 6/20/2006)RequestBnsf Railway Company
-
served (printed as 12/28/2005)DecisionDECISION GRANTED BNSF RAILWAY COMPANY'S REQUEST FOR AN EXTENSION OF TIME TO EXERCISE IT'S ABANDONMENT AUTHORITY UNTIL JULY 1, 2006.
-
(printed as 12/21/2005)RequestBnsf Railway Company
-
served (printed as 5/10/2005)DecisionEXTENDED THE TIME FOR BNSF TO CONSUMMATE THE ABANDONMENT AND TO FILE A NOTICE OF CONSUMMATION IN THIS PROCEEDING UNTIL DECEMBER 31, 2005.
-
(printed as 4/22/2005)RequestBnsf Railway Company
-
(printed as 1/13/2005)CommentRaymond V. Wallace
-
(printed as 1/7/2005)CommentRaymond V. Wallace
-
served (printed as 11/10/2004)DecisionREOPENED THE PROCEEDING TO REMOVE THE SIX ENVIRONMENTAL CONDITIONS IMPOSED IN THE BOARD'S JUNE 25, 2004 DECISION.
-
(printed as 10/27/2004)CommentDon Klima, Director
-
(printed as 9/17/2004)CommentDennis Gimmestad
-
(printed as 9/16/2004)CommentSue Fitzgerald
-
(printed as 9/2/2004)CommentJeff Johnson, Vice Chair
-
(printed as 8/16/2004)CommentDennis Gimmestad
-
(printed as 8/16/2004)CommentJohn Sims and Sidney Strickland
-
(printed as 8/16/2004)CommentDon L. Klima, Director
-
(printed as 8/12/2004)CommentJeff Johnson, Vice Chair
-
(printed as 7/20/2004)CommentMike Appel, Environmental Justice Coordinator
-
(printed as 7/9/2004)CommentSue Fitzgerald
-
served (printed as 6/25/2004)Decision(1) REOPENED THIS PROCEEDING; AND (2) IMPOSED SIX ENVIRONMENTAL CONDITIONS ON THE ABANDONMENT OF THE LINE.
-
(printed as 6/8/2004)CommentEI-863US EPA - Region 5Kenneth A. Westlake, Environmental Planning & Evaluation Branch
-
served (printed as 6/4/2004)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT REGARDING THE ENVIRONMENTAL ASSESSMENT.
-
(printed as 6/1/2004)CertificateBurlington Northern And Santa Fe Railway Company
-
served (printed as 5/28/2004)DecisionNOTICE THAT BNSF HAS FILED A NOTICE OF EXEMPTION TO ABANDON A 0.99-MILE LINE OF RAILROAD BETWEEN BNSF MILEPOST 11.81 AND MILEPOST 12.80 IN STILLWATER, WASHINGTON COUNTY, MN.
-
(printed as 5/12/2004)CommentEI-817Freeborn & Peters LLPBrian Nettles, Paralegal
-
(printed as 5/10/2004)Notice210820Notice Of ExemptionBurlington Northern And Santa Fe Railway Company
-
(printed as 5/5/2004)CommentEI-824National Geodetic SurveyNGS identified 1 geodetic survey marker that may be affected by the proposed abandonment.Richard A. Snay, Chief, Spatial Reference System Division
-
(printed as 4/19/2004)Environmental210634Environmental MaterialsBurlington Northern And Santa Fe Railway Company
Nothing of that kind in this docket.