Display Kept in this browser only
AB 1006-X · NEW YORK & GREENWOOD LAKE RAILWAY-ABANDONMENT EXEMPTION-IN PASSAIC, PASSAIC COUNTY, NJ

Decision 37881

Served (printed as 4/23/2007) · Decision · Director Of Proceedings

DECISION ORDERED THAT NEW YORK & GREENWOOD LAKE RAILWAY'S (NYGL) EXEMPTION TO ABANDON A .7-MILE LINE OF RAILROAD IN PASSAIC COUNTY, NJ, IS SUBJECT TO THE CONDITION THAT NYGL NOTIFY THE NATIONAL GEODETIC SURVEY (NGS) AT LEAST 90 DAYS PRIOR TO BEGINNING SALVAGE ACTIVITIES IN ORDER TO PLAN FOR THE POSSIBLE RELOCATION OF THE GEODETIC STATION MARKER BY NGS.

Read it here The text 37881.pdf ↓

Permanent address docketyard.org/decision/37881 · back to the docket sheet