AB 6 (Sub-No. 392X) · THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY--ABANDONMENT EXEMPTION--IN FLATHEAD COUNTY, MT

Decision 32704

Served (printed as 4/18/2002) · Decision · Director Of Proceedings

ORDERED THAT THE EXEMPTION OF THE ABANDONMENT OF THE LINE DESCRIBED IN THIS PROCEEDING IS SUBJECT TO THE CONDITION THAT BNSF: (1) RETAIN ITS INTEREST IN AND TAKE NO STEPS TO ALTER THE HISTORIC INTEGRITY OF ALL SITES OR STRUCTURES ON THE RIGHT-OF-WAY UNTIL COMPLETION OF THE SECTION 106 PROCESS OF THE NHPA; AND (2) NOTIFY NGS 90 DAYS PRIOR TO SALVAGE ACTIVITIES IN ORDER TO PLAN FOR RELOCATION OF ANY GEODETIC STATION MARKERS DISCOVERED ON THE LINE.

Read it here The text 32704.pdf ↓