NEW YORK CENTRAL LINES, LLC--ABANDONMENT EXEMPTION--IN MIDDLESEX COUNTY, MASS.
Caption from the Board’s record.
25 filings, 21 decisions and 0 environmental comments observed here; last checked 11 Oct 2026, 09:06 UTC; last new entry 26 Aug 2026, 15:37 UTC.
Entries
-
(printed as 2/7/2012)TrailCsx Transportation Inc
-
served (printed as 10/24/2011)DecisionDECISION GRANTED THE REQUEST FILED BY THE TOWN OF SHERBORN AND THE TOWN OF HOLLISTON TO EXTEND THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD TO AUGUST 22, 2011.
-
(printed as 9/14/2011)Reply230956ReplyCsx Transportation Inc
-
(printed as 9/13/2011)RequestTown Of Sherborn Massachusetts, Town Of Holliston Massachusetts
-
served (printed as 8/20/2010)DecisionDECISION GRANTED SHERBORN AND HOLLISTON'S REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD IN THIS PROCEEDING TO AUGUST 22, 2011.
-
(printed as 8/16/2010)Reply227649ReplyCsx Transportation Inc
-
(printed as 7/20/2010)RequestTown Of Holliston Massachusetts, Town Of Sherborn Massachusetts
-
served (printed as 3/5/2010)DecisionDECISION: (1) EXTENDED THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD TO AUGUST 22, 2010; AND (2) EXTENDED THE DEADLINE FOR CSX TRANSPORTATION, INC. TO FILE A NOTICE OF CONSUMMATION TO OCTOBER 21, 2010, IN THIS PROCEEDING.
-
(printed as 2/18/2010)Reply226454ReplyCsx Transportation Inc
-
(printed as 12/24/2009)RequestTown Of Holliston Massachusetts, Town Of Sherborn Massachusetts
-
served (printed as 3/20/2009)DecisionDECISION GRANTED THE REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD TO FEBRUARY 23, 2010, AND EXTENDED THE CONSUMMATION DEADLINE UNTIL APRIL 24, 2010.
-
(printed as 3/6/2009)Reply224636ReplyCsx Transportation Inc
-
(printed as 2/25/2009)RequestTown Of Sherborn MassachusettsTown Of Holliston Massachusetts
-
served (printed as 4/15/2008)DecisionDECISION GRANTED THE TOWN OF SHERBORN AND THE TOWN OF HOLLISTON'S REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD TO FEBRUARY 23, 2009, AND EXTENDED THE CONSUMMATION DEADLINE TO APRIL 24, 2009.
-
(printed as 4/10/2008)Reply222038ReplyCsx Transportation Inc
-
(printed as 4/1/2008)RequestTown Of Sherborn Massachusetts, Town Of Holliston Massachusetts
-
served (printed as 9/24/2007)DecisionDECISION GRANTED CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO FEBRUARY 23, 2008, AND ITS REQUEST FOR EXTENSION OF TIME TO EXERCISE ABANDONMENT AUTHORITY UNTIL APRIL 23, 2008.
-
(printed as 8/28/2007)RequestCsx Transportation Inc
-
served (printed as 8/8/2006)DecisionDECISION GRANTED THE REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE NEGOTIATING PERIOD UNTIL AUGUST 27, 2007.
-
(printed as 7/21/2006)Reply217111ReplyCsx Transportation Inc
-
(printed as 7/17/2006)RequestTown Of Holliston Massachusetts
-
(printed as 7/17/2006)RequestTown Of Sherborn Massachusetts
-
(printed as 3/2/2006)Reply215895ReplyTown Of Holliston Massachusetts
-
served (printed as 2/22/2006)DecisionDECISION GRANTED CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE NEGOTIATING PERIOD AND AN EXTENSION OF TIME TO EXERCISE ABANDONMENT AUTHORITY UNTIL AUGUST 21, 2006.
-
(printed as 2/17/2006)RequestCsx Transportation Inc
-
served (printed as 8/18/2005)DecisionEXTENDED THE NEGOTIATING PERIOD UNDER THE NITU TO FEBRUARY 22, 2006, AND EXTENDED THE TIME FOR CSXT TO EXERCISE THE ABANDONMENT AUTHORITY AND TO FILE A NOTICE OF CONSUMMATION TO ON OR BEFORE APRIL 26, 2006.
-
(printed as 7/29/2005)RequestCsx Transportation Inc
-
served (printed as 3/29/2005)DecisionGRANTED CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO AUGUST 26, 2005 AND ITS REQUEST FOR AN EXTENSION OF TIME TO EXERCISE ABANDONMENT AUTHORITY, WHICH MUST BE EXERCISED ON OR BEFORE OCTOBER 25, 2005.
-
(printed as 3/23/2005)RequestCsx Transportation Inc
-
served (printed as 9/9/2004)DecisionGRANTED CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO FEBRUARY 27, 2005 AND ITS REQUEST FOR AN EXTENSION OF TIME TO EXERCISE ABANDONMENT AUTHORITY, WHICH MUST BE EXERCISED ON OR BEFORE APRIL 28, 2005.
-
(printed as 9/7/2004)RequestCsx Transportation Inc, New York Central Lines Llc
-
served (printed as 2/10/2004)DecisionGRANTED NEW YORK CENTRAL LINES, LLC AND CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO AUGUST 27, 2004.
-
(printed as 1/21/2004)RequestNew York Central Lines Llc
-
served (printed as 8/27/2003)DecisionEXTENDED THE NITU NEGOTIATING PERIOD UNTIL FEBRUARY 27, 2004.
-
(printed as 8/15/2003)RequestNew York Central Lines Llc, Csx Transportation Inc
-
served (printed as 2/12/2003)DecisionGRANTED NEW YORK CENTRAL LINES, LLC AND CSX TRANSPORTATION, INC.'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO AUGUST 28, 2003.
-
(printed as 1/31/2003)RequestNew York Central Lines Llc
-
served (printed as 7/31/2002)DecisionEXTENDED THE NEGOTIATING PERIOD UNDER THE NITU TO FEBRUARY 28, 2003.
-
(printed as 7/11/2002)RequestCsx Transportation Inc, New York Central Lines Llc
-
served (printed as 5/1/2002)DecisionMODIFIED THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT SERVED SEPTEMBER 10, 2001, TO PROVIDE THE NYC RETAIN ITS INTEREST IN AND TAKE NO STEPS TO ALTER THE HISTORIC INTEGRITY OF THE BRIDGES IDENTIFIED (BOGASTOW BROOK BRIDGE, HIGHLAND STREET TUNNEL, THE ARCH STREET BRIDGE, THE EXCHANGE STREET RAILROAD BRIDGE AND THE WINTHROP CAN BRIDGE) UNTIL COMPLETION OF THE SECTION 106 PROCESS OF THE NHPA.
-
served (printed as 2/27/2002)DecisionEXTENDED THE NEGOTIATING PERIOD UNDER THE NITU TO AUGUST 28, 2002.
-
(printed as 2/22/2002)RequestNew York Central Lines Llc, Csx Transportation Inc
-
served (printed as 9/10/2001)Decision(1) REOPENED THIS PROCEEDING; AND (2) ORDERED THAT THE ABANDONMENT AUTHORITY GRANTED IN THIS PROCEEDING IS FURTHER SUBJECT TO THE CONDITION THAT NYC RETAIN ITS INTEREST IN AND TAKE NO STEPS TO ALTER THE HISTORIC INTEGRITY OF THE LINE UNTIL COMPLETION OF THE SECTION 106 PROCESS OF THE NHPA.
-
served (printed as 8/31/2001)Decision(1) REOPENED THIS PROCEEDING; (2) MODIFIED THE NOTICE OF EXEMPTION SERVED AND PUBLISHED IN THE FEDERAL REGISTER ON AUGUST 2, 2001, TO THE EXTENT NECESSARY TO IMPLEMENT INTERIM TRAIL USE/RAIL BANKING AS SET FORTH IN DECISION, SUBJECT TO THE CONDITIONS THAT CSXT KEEP INTACT THE RIGHT-OF-WAY UNDERLYING THE TRACK, INCLUDING BRIDGES, TRESTLES, CULVERTS AND TUNNELS (BUT NOT TRACK OR TRACK MATERIAL OR SIGNAL EQUIPMENT), FOR A PERIOD OF 180 DAYS FROM THE EFFECTIVE DATE (UNTIL FEBRUARY 28, 2002), TO ENABLE ANY STATE OR LOCAL GOVERNMENT AGENCY OR OTHER INTERESTED PERSON TO NEGOTIATE THE ACQUISITION OF THE LINE FOR PUBLIC USE.
-
served (printed as 8/7/2001)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT REGARDING THE ENVIRONMENTAL ASSESSMENT.
-
served (printed as 8/2/2001)DecisionNOTICE THAT NYC AND CSXT, HAVE FILED A NOTICE OF EXEMPTION FOR NYC TO ABANDON AND CSXT TO DISCONTINUE SERVICE NEAR SHERBORN AND HOLLISTON, IN MIDDLESEX COUNTY, MA.