(printed as 5/11/2026)NoticeLake State Railway Company
-
served (printed as 1/8/2026)DecisionREMOVED A PREVIOUSLY IMPOSED SECTION 106 CONDITION.
-
served (printed as 9/9/2025)DecisionPROVIDED A SUPPLEMENTAL FINAL ENVIRONMENTAL ASSESSMENT THAT RECOMMENDED THE BOARD REMOVE THE SECTION 106 CONDITION IMPOSED IN ITS JUNE 6, 2025 DECISION.
-
(printed as 9/4/2025)CommentScott Slagor · Lansing, MI
-
served (printed as 6/6/2025)DecisionMODIFIED A NOTICE OF EXEMPTION TO IMPOSE ENVIRONMENTAL CONDITIONS.
-
served (printed as 6/5/2025)DecisionRECOMMENDED THAT CONDITIONS PREVIOUSLY RECOMMENDED IN A DRAFT ENVIRONMENTAL ASSESSMENT SHOULD BE IMPOSED UPON A DECISION GRANTING ABANDONMENT AUTHORITY.
-
(printed as 5/30/2025)CommentKatlyn Burns Yancho · Lansing, MI
-
(printed as 5/30/2025)CommentThomas J. Litwiler · Chicago, IL
-
served (printed as 5/16/2025)DecisionPROVIDED A DRAFT ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED ABANDONMENT OF A LINE OF RAILROAD KNOWN AS THE WEST SHORE SPUR, APPROXIMATELY 6,805 FEET IN SAGINAW COUNTY, MICH.
-
served (printed as 5/9/2025)DecisionPROVIDED NOTICE THAT LAKE STATE RAILWAY COMPANY FILED A NOTICE OF EXEMPTION TO ABANDON APPROXIMATELY 6,805 FEET OF RAIL LINE IN SAGINAW COUNTY, MICH.
-
(printed as 5/1/2025)CommentProceedings
-
(printed as 4/21/2025)NoticeLake State Railway Company
-
(printed as 4/21/2025)CommentThomas J Litwiler · Chicago, IL
-
served (printed as 7/16/2007)DecisionDECISION DENIED LAKE STATE RAILWAY COMPANY'S PETITION SEEKING AN EXEMPTION TO ABANDON A 4.15-MILE LINE OF RAIL LINE IN OSTEGO COUNTY, MI, BECAUSE THE RECORD IS INADEQUATE FOR THE BOARD TO DETERMINE THAT AN ABANDONMENT EXEMPTION IS WARRANTED.
-
(printed as 6/28/2007)Comment
-
served (printed as 5/25/2007)DecisionCONCLUDED THAT THE ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT.
-
(printed as 5/7/2007)ReplyNorthern Energy, Inc.
-
(printed as 4/27/2007)ReplyLake State Railway Company
-
(printed as 4/25/2007)CommentProtest of abandonment and comments on environmental assessment attached.Jeff Ratcliffe · Gaylord, MI
-
(printed as 4/24/2007)ReplyOtsego County Economic Alliance
-
served (printed as 4/17/2007)DecisionPROVIDED NOTICE THAT LAKE STATE RAILWAY COMPANY FILED A NOTICE OF EXEMPTION TO PERMIT THE ABANDONMENT OF 4.15 MILES OF RAIL LINE IN OTSEGO COUNTY, MI.
-
(printed as 4/16/2007)CommentMartha MacFarlane Faes · Lansing, Michigan
-
(printed as 4/10/2007)ReplyCity Of Gaylord
-
(printed as 4/10/2007)Comment
-
(printed as 4/9/2007)TrailMichigan Department Of Natural Resources
-
(printed as 4/3/2007)Comment
-
(printed as 3/28/2007)MotionLake State Railway Company
-
served (printed as 5/6/2004)DecisionGRANTED MICHIGAN DEPARTMENT OF NATURAL RESOURCES' REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD TO OCTOBER 28, 2004.
-
(printed as 5/3/2004)RequestState Of Michigan Department Of Natural Resources
-
(printed as 5/3/2004)ReplyLake State Railway Company
-
served (printed as 4/22/2004)DecisionGRANTED LAKE STATE RAILWAY COMPANY'S REQUEST TO CLARIFY THE BOARD'S MAY 22, 2000 DECISION AND THE SUBSEQUENT DECISIONS IN THIS PROCEEDING; AND (2) MODIFIED THE DECISIONS TO SHOW THAT RCB MILEPOST 12.7 IS THE END POINT OF THE ROGERS CITY BRANCH.
-
(printed as 4/7/2004)MotionLake State Railway Company
-
served (printed as 11/10/2003)DecisionGRANTED LAKE STATE RAILWAY COMPANY'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD UNTIL MAY 1, 2004.
-
(printed as 11/10/2003)RequestState Of Michigan Department Of Natural Resources
-
(printed as 11/5/2003)RequestLake State Railway Company
-
served (printed as 8/8/2003)DecisionGRANTED LAKE STATE RAILWAY COMPANY'S REQUEST TO MODIFY THE MAY 23, 2003 DECISION TO INCLUDE INTERIM TRAIL USE/RAIL BANKING FOR THE PORTION OF THE RIGHT-OF-WAY EXTENDING FROM MILEPOST 6.7 TO MILEPOST 11.5 ON THE ROGERS CITY BRANCH.
-
(printed as 7/23/2003)MotionLake State Railway Company
-
served (printed as 5/23/2003)DecisionGRANTED LAKE STATE'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD UNTIL NOVEMBER 3, 2003, FOR THE PORTION OF LAKE STATE'S HURON SUBDIVISION EXTENDING NORTHWEST FROM THE U.S. HIGHWAY 23 CROSSING IN ALPENA (MILEPOST 125.2) TO THE END OF THE MAIN LINE JUST NORTH OF METZ, MI (MILEPOST 151.25), AND LAKE STATE'S ROGERS CITY BRANCH EXTENDING NORTHWARD FROM A POINT ON THE MAIN LINE AT POSEN, MI (MILEPOST 141.8), TO ROGERS CITY, MI, EXTENDING AT MILEPOST 6.7.
-
(printed as 5/19/2003)SupplementLake State Railway Company
-
(printed as 5/16/2003)RequestMichigan Department Of Natural Resources
-
(printed as 5/13/2003)LetterLake State Railway Company
-
(printed as 5/7/2003)RequestLake State Railway Company
-
(printed as 11/13/2002)RequestMichigan Department Of Natural Resources
-
served (printed as 11/8/2002)DecisionGRANTED LAKE STATE RAILWAY COMPANY'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD UNTIL MAY 7, 2003.
-
(printed as 11/6/2002)RequestLake State Railway Company
-
(printed as 6/6/2002)TrailMichigan Department Of Natural Resources
-
served (printed as 5/17/2002)DecisionGRANTED LAKE STATE'S REQUEST TO EXTEND THE NITU NEGOTIATING PERIOD UNTIL NOVEMBER 8, 2002.
-
(printed as 5/10/2002)RequestLake State Railway Company
-
(printed as 1/31/2002)RequestLake State Railway Company
-
(printed as 1/7/2002)RequestMichigan Department Of Natural Resources
-
served (printed as 12/18/2001)DecisionGRANTED THE REQUESTS OF LAKE STATE AND MIDNR TO EXTEND THE NITU NEGOTIATING PERIOD FOR 180 DAYS UNTIL MAY 12, 2001.
-
served (printed as 5/4/2001)DecisionGRANTED LAKE STATE'S REQUEST TO EXTEND THE NEGOTIATING PERIOD UNDER THE NITU UNTIL NOVEMBER 3, 2001.
-
served (printed as 4/27/2001)DecisionGRANTED THE PARTIES REQUEST TO EXTEND THE NEGOTIATING PERIOD UNDER THE NITU TO OCTOBER 16, 2001.
-
served (printed as 11/21/2000)DecisionGRANTED MDNR'S REQUEST TO EXTEND THE NEGOTIATING PERIOD UNDER THE NITU TO APRIL 29, 2000.
-
served (printed as 11/17/2000)DecisionGRANTED MIDNR AND LAKE STATE'S REQUEST TO EXTEND THE NEGOTIATING PERIOD UNDER THE NITU FOR 180 DAYS UNTIL MAY 17, 2001.
-
served (printed as 5/22/2000)DecisionEXEMPTED UNDER 49 U.S.C. 10502, FROM THE PRIOR APPROVAL REQUIREMENTS OF 49 U.S.C. 10903, THE ABANDONMENT BY LAKE STATE OF 37.55 MILES OF RAIL LINE, IN ALPENA AND PRESQUE ISLE COUNTIES, MI, SUBJECT TO TRAIL USE, PUBLIC USE, ENVIRONMENTAL AND STANDARD EMPLOYEE PROTECTIVE CONDITIONS.
-
served (printed as 5/12/2000)DecisionGRANTED MDNR AND LAKE STATE'S REQUEST TO EXTEND THE NEGOTIATING PERIOD UNDER THE NITU TO OCTOBER 31, 2000.
-
served (printed as 3/31/2000)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT REGARDING THE ENVIRONMENTAL ASSESSMENT.
-
served (printed as 2/22/2000)DecisionNOTICE THAT LAKE STATE FILED WITH THE BOARD A PETITION UNDER 49 U.S.C. 10502 FOR EXEMPTION FROM THE PROVISIONS OF 49 U.S.C. 10903 TO ABANDON: (1) A PORTION OF ITS MAIN LINE HURON SUBDIVISION EXTENDING FROM THE U. S. HIGHWAY 23 CROSSING IN ALPENA NORTHWARD TO THE END OF THE MAIN LINE JUST NORTH OF METZ, MI; AND (2) ITS ENTIRE ROGERS CITY BRANCH , WHICH EXTENDS NORTHWARD FROM LAKE STATE'S MAIN LINE AT POSEN, MI, TO ROGERS CITY, MI, WHERE IT ENDS AT RCB MILEPOST 11.5.
-
served (printed as 11/5/1999)Decision(1) PLACED MR. GRIFFITH'S LETTER OF OCTOBER 28, 1999, IN THE PUBLIC DOCKET AND WILL BE TREATED AS CORRESPONDENCE; AND (2) EXTENTED MDNR AN ADDITIONAL NEGOTIATING PERIOD UNDER THE NITU UNTIL MAY 4, 2000.
-
served (printed as 5/13/1999)DecisionEXTENDED MDNR'S NEGOTIATING PERIOD UNDER THE NITU UNTIL NOVEMBER 6, 1999
-
served (printed as 11/19/1998)DecisionEXTENDED MDNR'S NEGOTIATING PERIOD UNDER THE NITU TO MAY 10, 1999.
-
served (printed as 5/15/1998)DecisionEXTENDED MDNR'S NEGOTIATING PERIOD UNDER THE NITU UNTIL NOVEMBER 11, 1998.
-
served (printed as 12/1/1997)DecisionFOUND THAT NO SIGNIFICANT IMPACT UNDER 49 CFR 1105.10(G) WILL BE MADE PURSUANT TO 49 CFR 1011.8(C)(10).
-
served (printed as 11/18/1997)DecisionREOPENED THIS PROCEEDING AND MODIFIED TO THE EXTENT NECESSARY TO IMPLEMENT INTERIM TRAIL USE/RAIL BANKING AS SET FORTH IN THIS PROCEEDING.
-
served (printed as 10/24/1997)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENTS REGARDING THE ENVIRONMENTAL ASSESSMENT.
-
served (printed as 10/17/1997)DecisionNOTICE OF ABANDONMENT EXEMPTION AND ESTABLISHED A PROCEDURAL SCHEDULE.