BIRMINGHAM SOUTHERN RAILROAD COMPANY
Caption from the Board’s record. Sub-dockets, included below: AB 192 (Sub-No. 1), AB 192 (Sub-No. 2X)
8 filings, 6 decisions and 5 environmental comments observed here; last checked 10 Oct 2026, 22:36 UTC; last new entry 31 Aug 2026, 20:18 UTC.
Entries
-
(printed as 7/22/2008)NoticeBirmingham Southern Railroad Company
-
(printed as 4/10/2008)NoticeBirmingham Southern Railroad Company
-
(printed as 4/25/2007)EnvironmentalBirmingham Southern Railroad Company
-
(printed as 2/15/2007)CommentColonel (Ret.) John A. Neubauer, SHPO
-
served (printed as 1/22/2007)DecisionDECISION REOPENED THIS PROCEEDING AND IMPOSED CONDITIONS FOR THE ABANDONMENT EXEMPTION.
-
(printed as 1/22/2007)CommentChristopher Ford, Resource Soil Scientist
-
(printed as 1/18/2007)Comment
-
(printed as 1/17/2007)CommentRon Johnson
-
served (printed as 12/29/2006)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT REGARDING THE ENVIRONMENTAL ASSESSMENT.
-
served (printed as 12/22/2006)DecisionPROVIDED NOTICE THAT BIRMINGHAM SOUTHERN RAILROAD COMPANY FILED A VERIFIED NOTICE OF EXEMPTION UNDER 49 CFR 1152 SUBPART F TO ABANDON A 0.18-MILE LINE OF RAILROAD KNOWN AS THE OLD PORT BRANCH, EXTENDING FROM SURVEY STATION 936+04.07 OF TURNOUT P-63 A, OVER TRESTLE 17.9, TO A CONNECTION WITH ERGON TERMINALING, INC.'S RAIL LINE AT SURVEY STATION 945+52.55 IN JEFFERSON COUNTY, AL.
-
(printed as 12/14/2006)CommentAnne Newman
-
(printed as 12/12/2006)SupplementBirmingham Southern Railroad Company
-
(printed as 12/12/2006)EnvironmentalBirmingham Southern Railroad Company
-
(printed as 12/11/2006)CorrectionBirmingham Southern Railroad Company
-
(printed as 12/5/2006)MotionBirmingham Southern Railroad Company
-
(printed as 11/29/2006)NoticeBirmingham Southern Railroad Company
-
served (printed as 4/29/1998)DecisionGRANTED BS'S APPLICATION TO ABANDON 3.869 MILES OF ITS RAILROAD LINE IN JEFFERSON COUNTY, AL, AND TO DISCONTINUE ITS TRACKAGE RIGHTS OVER .614 MILES OF NSR'S RAILROAD LINE IN JEFFERSON COUNTY, AL, SUBJECT TO THE STANDARD LABOR PROTECTIVE CONDITIONS, AND ESTABLISHED A PROCEDURAL SCHEDULE.
-
served (printed as 1/29/1998)DecisionNOTICE OF ABANDONMENT AND DISCONTINUANCE OF TRACKAGE RIGHTS; AND ESTABLISHED A PROCEDURAL SCHEDULE.
-
served (printed as 1/23/1998)DecisionCONCLUDED THAT AN ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENTS REGARDING THE ENVIRONMENTAL ASSESSMENT.
Nothing of that kind in this docket.