Display Kept in this browser only
Finance DocketBefore the Surface Transportation Board

FD 33862

PUBLIC SERVICE COMPANY OF COLORADO--CONSTRUCTION EXEMPTION--PUEBLO COUNTY, CO

Caption from the Board’s record. Sub-dockets, included below: FD 33862 (Sub-No. 1)

1 filing, 8 decisions and 0 environmental comments observed here; last checked 10 Oct 2026, 21:36 UTC; last new entry 26 Aug 2026, 15:18 UTC.

Entries

By type (1)
Newest first · oldest first
  1. Decision
    31743Secretary
    NOTICE THAT A COURT ACTION WAS INSTITUTED ON OR ABOUT MARCH 9, 2001, BEFORE THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT.
  2. Decision
    31499Entire Board · in FD 33862 (Sub-No. 1)
    (1) GRANTED PSCO'S TRACK CROSSING REQUEST UNDER 49 U.S.C. 10901(D); (2) ORDERED PSCO AND BNSF THAT WITHIN 45 DAYS OF SERVICE OF THIS DECISION TO NEGOTIATE THE COMPENSATION AND ANY REMAINING TERMS FOR THE CROSSING, AND PSCO SHALL FILE A REPORT WITH THE BOARD; AND (3) FOUND THAT THE BOARD SERVES JURISDICTION OVER THIS PROCEEDING UNTIL SUCH TIME AS THE PARTIES HAVE REACH A CROSSING AGREEMENT.
  3. Decision
    31403Entire Board
    (1) ADOPTED THE ENVIRONMENTAL MITIGATION MEASURES AND IMPOSE THEM AS A CONDITION TO THE EXEMPTION GRANTED IN THIS PROCEEDING; AND (2) ORDERED THAT THE EXEMPTION CONDITIONALLY APPROVED IN THE AUGUST 23, 2000 DECISION IS EFFECTIVE 30 DAYS FROM THE DATE OF SERVICE OF THIS DECISION, SUBJECT TO THE CONDITION THAT PSCO COMPLY WITH THE MITIGATION MEASURES IMPOSED IN THIS DECISION WITH RESPECT TO THE CONSTRUCTION AND OPERATION OF THE INVOLVED RAIL LINE.
  4. Decision
    31462Secretary · also entered in FD 33862 (Sub-No. 1)
    NOTICE THAT A COURT ACTION WAS INSTITUTED ON OR ABOUT OCTOBER 20, 2000, BEFORE THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT.
  5. Decision
    31058Entire Board · in FD 33862 (Sub-No. 1)
    (1) DENIED THE MOTION TO DISMISS THE CROSSING PETITION FILED BY BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY; AND (2) ESTABLISHES A PROCEDURAL SCHEDULE UNDER THE MODIFIED PROCEDURE.
  6. Decision
    31125Chief Of Section Of Environmental Analysis
    CONCLUDED THAT THIS PROPOSAL WOULD NOT SIGNIFICANTLY AFFECT THE QUALITY OF THE NATURAL OR HUMAN ENVIRONMENT PROVIDED THE RECOMMENDED MITIGATION MEASURES SET FORTH IN SEC. 6.0 ARE IMPLEMENTED.
  7. Decision
    30988Entire Board
    GRANTED A CONDITIONAL EXEMPTION UNDER 49 U.S.C. 10502, FROM THE PRIOR APPROVAL REQUIREMENTS OF 49 U.S.C. 10901, THE CONSTRUCTION BY PSCO'S OF A LINE OF RAILROAD, APPROXIMATELY 1,500 FEET IN LENGTH, IN PUEBLO COUNTY, CO.
  8. Decision
    31153Secretary
    INSTITUTED A PROCEEDING UNDER 49 U.S.C. 10502(B) TO CONSIDER PSCO'S PETITION AND THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY'S MOTION TO DISMISS.
  9. Environmental
    197900Environmental Materials
    Colorado Public Service Co