Finance DocketBefore the Surface Transportation Board

FD 33740

THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY--PETITION FOR DECLARATION OR PRESCRIPTION OF CROSSING, TRACKAGE, OR JOINT USE RIGHTS

Caption from the Board’s record. Sub-dockets, included below: FD 33740 (Sub-No. 1)

18 filings, 14 decisions and 0 environmental comments observed here; last checked 10 Oct 2026, 21:36 UTC; last new entry 26 Aug 2026, 15:23 UTC.

Entries

By type (6)
Newest first · oldest first
  1. Decision
    34174Secretary · also entered in FD 33740 (Sub-No. 1)
    GRANTED THE PARTIES' JOINT REQUEST TO TERMINATE AND DISCONTINUE THESE PROCEEDINGS.
  2. Motion
    209284Motion To Dismiss Or Discontinue
    Burlington Northern And Santa Fe Railway Company
  3. Misc.
    209234Miscellaneous · in FD 33740 (Sub-No. 1)
    Baker & Miller Pllc
  4. Misc.
    209231Miscellaneous
    Baker & Miller Pllc
  5. Decision
    34120Secretary
    EXTENDED THE DEADLINE FOR SUBMISSION OF ANY DISPUTED COMPENSATION OR OTHER CROSSING TERMS FOR BOARD RESOLUTION UNTIL NOVEMBER 12, 2003.
  6. Letter
    209117Letter
    Keokuk Junction Railway Company
  7. Request
    209116Request For Extension Of Time
    Burlington Northern And Santa Fe Railway Company
  8. Decision
    34014Secretary
    EXTENDED, UNTIL OCTOBER 13, 2003, THE DEADLINE FOR SUBMITTING MATTERS OF DISPUTED COMPENSATION OR OTHER CROSSING TERMS TO THE BOARD FOR RESOLUTION.
  9. Request
    208905Request For Extension Of Time
    Keokuk Junction Railway Company, Burlington Northern And Santa Fe Railway Company
  10. Decision
    33925Secretary
    GRANTED THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY'S REQUEST FOR AN EXTENSION TO CONTINUE NEGOTIATIONS UNTIL SEPTEMBER 12, 2003.
  11. Request
    208677Request For Extension Of Time
    Burlington Northern And Santa Fe Railway Company, Keokuk Junction Railway Company
  12. Decision
    33832Secretary
    GRANTED THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY'S REQUEST FOR AN EXTENSION OF TIME UNTIL AUGUST 13, 2003.
  13. Request
    208382Request For Extension Of Time
    Keokuk Junction Railway Company, Burlington Northern And Santa Fe Railway Company
  14. Letter
    208327Letter · in FD 33740 (Sub-No. 1)
    Keokuk Junction Railway Company
  15. Letter
    208326Letter
    Keokuk Junction Railway Company
  16. Decision
    33639Secretary
    NOTICE THAT A COURT ACTION WAS INSTITUTED ON OR ABOUT MAY 20, 2003, BEFORE THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT.
  17. Decision
    32916Entire Board
    (1) GRANTED THE BURLINGTON NORTHERN AND SANTA FE RAILWAY COMPANY'S (BNSF) REQUEST FOR ISSUANCE OF A CERTIFICATE PURSUANT TO 49 U.S.C. 10901; (2) ORDERED THAT, PURSUANT TO SECTION 10901(D), KEOKUK JUNCTION RAILWAY COMPANY (KJRY) MUST ALLOW BNSF TO CROSS KJRY'S LINE TO REACH THE MOOAR LINE; (3) DIRECTED THE PARTIES TO IMMEDIATELY BEGIN NEGOTIATIONS ON A NEW CROSSING AGREEMENT; AND (4) CONCLUDED THAT, IF THE PARTIES ARE UNABLE TO AGREE WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THIS DECISION ON COMPENSATION OR OTHER CROSSING TERMS, EITHER OR BOTH PARTIES SHALL SUBMIT THE MATTERS IN DISPUTE TO THE BOARD, WHICH WILL MAKE A DETERMINATION WITHIN 120 DAYS THEREAFTER.
  18. Decision
    33578Secretary
    NOTICE THAT THE BOARD WILL CONDUCT A VOTING CONFERENCE ON FRIDAY, MAY 9, 2003, AT 10 A.M.
  19. Letter
    205942Letter
    Burlington Northern And Santa Fe Railway Company
  20. Reply
    205892Reply
    Keokuk Junction Railway Company
  21. Motion
    205845Motion/Petition/Request
    Burlington Northern And Santa Fe Railway Company
  22. Reply
    205096Reply · in FD 33740 (Sub-No. 1)
    Burlington Northern And Santa Fe Railway Company
  23. Reply
    205095Reply · in FD 33740 (Sub-No. 1)
    Keokuk Junction Railway Company
  24. Statement
    204882Verified Statement · in FD 33740 (Sub-No. 1)
    Richard J Lane Sr
  25. Statement
    204877Opening Statement · in FD 33740 (Sub-No. 1)
    Burlington Northern And Santa Fe Railway Company
  26. Statement
    204873Opening Statement · in FD 33740 (Sub-No. 1)
    Keokuk Junction Railway Company
  27. Decision
    32336Secretary · in FD 33740 (Sub-No. 1)
    ORDERED: (1) OPENING STATMENTS FROM BNSF AND KJRY ADDRESSING ALL OF THE ISSUES TO BE RESOLVED BY THE BOARD ARE DUE BY MARCH 1, 2002; AND (2) REPLY STATEMENTS ARE DUE BY APRIL 1, 2002.
  28. Decision
    32227Secretary · in FD 33740 (Sub-No. 1)
    EXTENDED THE MEDIATION PERIOD FOR AN ADDITIONAL 30 DAYS.
  29. Decision
    32086Entire Board · in FD 33740 (Sub-No. 1)
    ASSIGNED FOR A 30-DAY PERIOD ALJ NACY,OF FERC TO MEDIATE A DISPUTE BETWEEN THE PARTIES AND SETS INTERIM COMPENSATION FOR BNSF TO CROSS KJRY'S LINE AT THE AMOUNT AGREED TO PRIOR TO THE PARTIES DISPUTE.
  30. Decision
    32016Secretary · also entered in FD 33740 (Sub-No. 1)
    NOTICE THAT A COURT ACTION WAS INSTITUTED ON OR ABOUT JULY 11, 2001, BEFORE THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT.
  31. Decision
    31332Entire Board · also entered in FD 33740 (Sub-No. 1)
    (1) GRANTED BNSF'S REQUEST FOR DECLARATORY RELIEF; (2) ORDERED KJRY, PURSUANT TO SECTION 10901(D) TO ALLOW BNSF TO CROSS KJRY'S LINE TO REACH THE MOOAR LINE; (3) DENIED BNSF'S PETITION FOR DETERMINATION OF TERMS AS PREMATURE; (4) DIRECTED THE PARTIES TO IMMEDIATELY BEGIN NEGOTIATIONS ON A NEW CROSSING AGREEMENT; AND (5) INSTRUCTED THE PARTIES TO SUBMIT DISPUTES TO THE BOARD, WHICH WILL MAKE A DETERMINATION WITHIN 120 DAYS THEREAFTER.
  32. Decision
    30411Entire Board · also entered in FD 33740 (Sub-No. 1)
    (1) DIRECTED ALL INTERESTED PARTES TO SUBMIT FURTHER EVIDENCE AND ARGUMENT REGARDING THE REASONABLENESS OF THE PARTIES' CURRENT INTERCHANGE OPERATION UNDER 49 U.S.C. 10742; AND (2) ALLOWED 50 DAYS FROM THE SERVICE DATE OF THIS DECISION FOR ALL INTERESTED PARTIES TO SUBMIT WRITTEN CROSS-REPLIES.